¿ªÔÆÌåÓý

¿ªÔÆÌåÓý is independent, community-supported media, serving Vermont with trusted, relevant and essential information. We share stories that bring people together, from every corner of our region. New to ¿ªÔÆÌåÓý? Start here.

© 2025 ¿ªÔÆÌåÓý | 365 Troy Ave. Colchester, VT 05446

Public Files:
· · · ·
· · · ·
· · · ·
· ·

For assistance accessing our public files, please contact [email protected] or call 802-655-9451.
Play Live Radio
Next Up:
0:00
0:00
0:00 0:00
Available On Air Stations

Explore our coverage of government and politics.

State Supreme Court Wants Additional Review of Vermont Gas Pipeline Cost Overruns

Exterior of the Vermont Gas building.
Taylor Dobbs
/
VPR File
The state Supreme Court has sent a Vermont Gas case back to the Public Utility Commission for a closer look at cost overruns on its Addison pipeline project.

The Vermont Supreme Court a state utility board to reopen a Vermont Gas Systems rate case involving tens of millions of dollars in cost overruns for its Addison County natural gas pipeline.

The 41-mile long pipeline serves about 2,000 customers but cost around $165 million � and that price tag roughly doubled over the last several years. The high court wants to know if ratepayers were fully protected from the unanticipated increase.

Although the state's  did remove about $31 million from the overall amount customers have to cover, the court wrote late last week that “There are no findings that allow this Court to understand how the Commission arrived at this conclusion.â€� 

James Dumont, who represents AARP in the rate case and the appeal to the Vermont Supreme Court, said Vermont Gas � not its customers � should be on the hook for more of the cost overruns. AARP has argued in several cases for lower rates on behalf of its members and other customers.

"The evidence showed massive imprudence due to lack of knowledgeable staff running the company and running this project." � AARP lawyer James Dumont

“The evidence showed massive imprudence due to lack of knowledgeable staff running the company and running this project,â€� Dumont said.

And Dumont offered this primer on the legal meaning of the word “prudent�: He notes that law and legal precedent say that a regulated monopoly, such as a utility, can only charge customers for costs that are prudent � that is, are thoroughly documented and justified.

“Some of the [legal] treatises say that this prudence review is regulation’s principle substitute for the forces of the free market,� Dumont said. “Customers can’t get up and leave, so the utility commission has to do the work for them and say, 'Well we’re gonna disallow those costs that weren’t prudently incurred.'�

Dumont said the record shows that the company grossly mismanaged the project. For example, the state hired an expert to look at the ballooning costs of the pipeline.

“He reviewed this enormous body of documents, and he concluded there was no evidence that anything spent over the original $86 million had been prudently incurred,� Dumont said.

"We appreciate the thorough review from the Supreme Court, and we plan on working closely with the PUC to resolve this matter." � Beth Parent, Vermont Gas spokeswoman

Vermont Gas spokeswoman Beth Parent said the company welcomes the new review.

“We appreciate the thorough review from the Supreme Court, and we plan on working closely with the PUC to resolve this matter,� Parent said.

James Porter, the public advocate for ratepayers, said the Vermont Department of Public Service has already closely examined the cost overruns.

Porter said the department is ready to keep digging into what costs for the pipeline were justified.

"I think we’ll have to see what the commission does with the remand and obviously the department will be supportive of whatever process they feel is necessary,� Porter said.

Disclosure: AARP Vermont is a VPR underwriter.

John worked for VPR in 2001-2021 as reporter and News Director. Previously, John was a staff writer for the Sunday Times Argus and the Sunday Rutland Herald, responsible for breaking stories and in-depth features on local issues. He has also served as Communications Director for the Vermont Health Care Authority and Bureau Chief for UPI in Montpelier.

Have questions, comments or tips? Send us a message.

Loading...


Latest Stories